Chapter 20: Project Management
++
++
++
Which one of the following best describes a project?
++
++
++
a. Ongoing, day-to-day activities that support an organization
++
++
b. A group of plans that support an overall strategic organizational objective
++
++
c. A finite, progressively elaborate endeavor with a beginning and end
++
++
d. An endeavor with a larger scope than either a program or portfolio
++
++
+
++
c. A finite, progressively elaborate endeavor with a beginning and end
++
++
++
Which one of the following is used to define/identify when a project is complete?
++
++
++
++
++
++
++
c. Work breakdown structure (WBS)
++
++
++
++
+
++
++
++
++
Which of the following considerations is important when determining the value proposition of a project?
++
++
++
a. Measurable and quantifiable
++
++
b. Aligned with the priorities of the organization
++
++
c. Related to financial incentives or profits
++
++
++
++
+
++
++
++
++
A pharmacist wants to conduct a project to standardize how concentrated 23.4% normal saline is stored and dispensed within a hospital. After discussing the project with leadership the pharmacist decides to develop a project charter.
++
Which one of the following individuals would NOT be considered a stakeholder for this project?
++
++
++
a. Nurse manager in the neuro intensive care unit
++
++
b. Inpatient pharmacy operations manager
++
++
c. Medication safety officer for the hospital
++
++
d. Physician chair of intensive medicine for the hospital
++
++
e. Radiology technician in the medical intensive care unit
+
++
e. Radiology technician in the medical intensive care unit
++
++
++
A pharmacist wants to conduct a project to standardize how concentrated 23.4% normal saline is stored and dispensed within a hospital. After discussing the project with leadership the pharmacist decides to develop a project charter.
++